Timeline

Check-in on the project’s status. This page will be updated as we move throughout the development process.

Timeline

Continue to check back here for updates to the project timeline.

  • Jul 23, 2020

    June 2020

    Letters mailed to adjacent neighbours

  • Jul 23, 2020

    July 2020

    Virtual Meeting with SERRA and LRA

  • Jul 23, 2020

    July 2020

    Call with Bayview Leaside BIA

  • Nov 4, 2020

    October 23, 2020

    Application Submission

  • Feb 22, 2021

    February 17, 2021

    Virtual Meeting with Bayview Leaside BIA

  • Feb 22, 2021

    March 1, 2021

    Preliminary Report brought to North York Community Council 

  • Apr 22, 2021

    May 13, 2021

    City-led Community Consultation Meeting. View presentation here 

  • Jan 4, 2022

    August 2021

    Site visits with adjacent neighbours

  • Jan 4, 2022

    December 23, 2021

    Application resubmission. View materials here

  • Jul 26, 2023

    25 May, 2022

    Application resubmission. View materials here

  • Jul 21, 2023

    June 14, 2023

    Settlement offer reached with the City

  • Jul 21, 2023

    July 2023

    Updates to adjacent neighbours, Bayview Leaside BIA, SERRA and LRA

subfooter_icon

What do you think?

We want to hear your thoughts, perspectives, and questions.